Re: Report to check the assignment of resource for a WBS

$
0
0

Hi Shiv,

 

For WBS project team there is no standard report,you have to go with development for it.

 

Pointers on it are as follows:

 

Use tables PRPS and HRP1001 , In HRP1001 you will get object type (OTYPE) filter it for either P (person) or S (position) or both. You can write a SQVI query or infoset query to develop your own report using these fields.

Hope it will help you.

 

Thanks


Viewing all articles
Browse latest Browse all 8411

Trending Articles


FLASHBACK WITH SIRASA FM AT GALGAMUWA 2022


Mp3 Download: Mdu - Mazola


Imitation gun was fired at motorist in Leicester road-rage incident


Ndebele names


MCKINNEY EMALINE “EMMA” OF WES...


Okra & Motia — The Workshop (Prod by Hammer)


Skint TV teen to be sentenced


Moondru Mudichu 19-09-2017 – Polimer tv Serial


YOSVANI JAMES Arrested by Miami-Dade County Corrections on Jan 10, 2017


Stories • Goddess Stepmom



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>