Thanks Avinash,
Let me try explaining my condition.
I am a sheet metal fabricator. I buy Sheet metal (Dimensional Product L X B X W )
Now as per my BOM Definition for a Semi Finished product:
For CNC Milling operation I, produce 5 SFG-1 from this sheet metal (1 unit sheet ) and also 2 SFG-2 which I don't require but also is recd. along with some scrap, which I would be interested to sell eventually.
Input Material:
1 Unit sheet = 6M X 3M X 1M
Its weight is : 5 Tonnes
Output Material:
SFG-1: 5 Pc
SFG-2: 3 Pc (Can be called by product as after 5 SFG-1, 3
SFG-2 can be also produced )
Scrap : 200 Kg
I am also interested in raw material consumed in SFG-2
Now, how should be the bom for SFG-1 be designed.
Please advice
Vivek